Monday, June 3, 2013

18 days to go

Yep! We were delayed by a week for our handover date – which is now set for 20 June – which means we have the same wait as last week >insert massive sad face here< but it looks like it won’t get delayed again as all the paper work and final invoice has been set out and everything seems to be lock and loaded for the 20th yay!
The past week and all the weeks leading up to handover are going to be a little crazy. Alex and I have been calling and arranging for all of our post-handover work to be booked in and ready to go – which is looking a little like this:
Electrical work
Install wood flooring
Install carpet
Delivery of new bed  
Delivery of POD
Pest control
Driveway
Excavation work
Portico and Alfresco decks
Fence
Turf  

Crazy times!!

Alex and I managed to complete the first coat of paint over the entire fence, with the help of Mindy on Sunday! The fence is looking 10x better, I forgot to get a picture of it when we were done so you will have to wait until next week to see it. The house was also fitted out during the week which we went over with a fine tooth comb – on close inspection they’ve made quite a mess and chipped and cracked a whole heap of paint and wood and some things are crooked and finished off rather carelessly to be honest! The supervisor will be finding out about these during this week.

On a whole, everything is looking great though.   









No comments: